Project Description:
The project consists of:
Street Improvements.
-
Judson Street: From Seminary Street to 39’ East of Poplar Street
|
Approx. 1540x20 L.F. of Milling and Resurfacing. Also included is Full Depth Patching, Concrete Curb Installation, Storm Inlet Installation, and Storm Drainage Pipe Installation
|
-
Jefferson Street: From Mechanic Street to Mill Street
|
Approx. 1570x23 L.F. of Milling and Resurfacing. Also included is Catch Basin Reconstruction, Curb Ramp Installation, Sidewalk Replacement, and Poured-in-Place Retaining Wall Replacement.
|
-
Jefferson Street: From Mechanic Street to US 231
|
Approx. 600x29 L.F. Of Milling and Resurfacing. Also included is Curb Ramp Installation, Full Depth Patching, and Transverse Crosswalk Marking Installation.
|
-
Lester Street: From SR 54 to Spring Street
|
Approx. 1071x16 L.F. of Milling and Resurfacing. Also included and Catch Basin Reconstruction.
|
| Project Date: | 01/13/2026 | | Date Due: | 02/03/2026 | | Company: | Patriot Municipal Utilities | | Bid Notice: | Notice to Bidders.pdf |
Project Description:
The project consists of:
Street Improvements and Stormwater Improvements.
-
Plum Street: From Plum Valley Road to SR 156/ Main Street
|
Approx. 15x200 L.F. of Milling, Resurfacing, and Road Widening with HMA
|
-
Plum Street: From 5th Street to Plum Valley Road
|
Approx. 16x1265 L.F. of Milling, Resurfacing, and Full Depth Patchin
|
-
Fifth Street: From SR 156/ Main Street to Plum Street
|
Approx. 15x268 L.F. of Milling, and Resurfacing
|
-
First Street: From SR 156/ Main Street to Plum Street
|
Approx. 14x335 L.F. of Milling and Resurfacing
|
-
First Street: From SR 156/ Main Street to Front Street
|
Approx. 16x280 L.F. of Milling and Resurfacing
|
-
Front Street: From Third Street to First Street
|
Approx. 11x623 L.F. of Milling and Resurfacing
|
Project Description:
The project consists of:
Street Improvements.
-
Wood Street: From Walker Street to 70’ SW to 70’ West of Main Street
|
Approx. 470’x 39’ L.F. of Milling and Resurfacing, Curb Installation, Culvert Replacement, Sidewalk Replacement, Concrete Approach Installation, and Curb Ramp Installation
|
-
Wood Street: From West First Street to US 231
|
Approx. 270’ x 39’ L.F. of Milling and Resurfacing, Curb Installation, Reconstruction of a catch basin, Sidewalk Replacement, Concrete Approach Installation, and Curb Ramp Installation
|
-
East Third Street: From US 50 to Terminus
|
Approx. 1,600’ x 19’ L.F. of Milling and Resurfacing, Curb Installation, Sidewalk Removal and Replacement, Concrete Approach Installation, Curb Inlet Installation, Culvert Replacement, Linear Grading, and Riprap Installation
|
-
South Oak Street: From Pine Street to Elm Street
|
Approx. 1,030’ x 35’ L.F. of Milling and HMA Resurfacing, Sidewalk Replacement, Concrete Approach Installation, and Linear Grading
|
-
Sycamore Street: From Clark Street to Terminus
|
Approx. 450’ x 18’ L.F. of Milling and Resurfacing
|
-
Mulberry Street: From Williams Street to Vincennes Street
|
Approx. 1,300’ x 17’ L.F. of Milling and Resurfacing, Sidewalk Replacement, and Crosswalk Marking Installation
|
-
Doyle Street: From Acton Avenue to Terminus
|
Approx. 1,500’ x 20’ L.F. of Milling and Resurfacing
|
-
Walnut Street: From Oak Street to Terminus
|
Approx. 1,440’ x 18’ L.F. of Milling and Resurfacing, Sidewalk Replacement, Culvert Replacements, Curb Inlet Installations, Riprap Installation, and Seeding
|
-
Poplar Street: From Elm Street to East First Street
|
Approx. 1,660’ x 19’ L.F. of Milling and Resurfacing
|
Project Description:
The project consists of:
Street Improvements and Stormwater Improvements.
-
CR 2000 N: From N Washington Street to Cul-De-Sac
|
Approx. 21x1500 L.F. of Milling, Full Depth Patching, and Resurfacing
|
-
Vine Street: From S Main Street to Dunn Street
|
Approx. 20x1400 L.F. of Milling and Resurfacing.
|
-
Locust Street: From N Washington Street to Wallace Street
|
Approx. 20x600 L.F. of Milling and Resurfacing
|
-
Burress Road: From N Washington Street to US 231
|
Approx. 50x520 L.F. of Milling, Full Depth Patching, and Resurfacing
|
-
Wallace Street: From SR 62 to Hammond Street
|
Approx. 26x320 L.F. of Milling, and Resurfacing
|
-
Wallace Street: From Vine Street to SR 62
|
Approx. 32x780 L.F. of Milling and Resurfacing
|
-
Gains Street: From Vine Street to Maple Street
|
Approx. 19x500 L.F. of Milling and Resurfacing
|
-
Gains Street: From SR 62 to Vine Street
|
Approx. 18x1000 L.F. of Milling and Resurfacing
|
-
Wallace Street: From Brown Avenue to Cherry Street
|
Approx. 18x320 L.F. of Milling and Resurfacing
|
-
Cherry Street: From Wallace Street to Gains Street
|
Approx. 18x480 L.F. of Milling and Resurfacing
|
-
Cherry Street: From N Washington Street to Walnut Street
|
Approx. 16x330 L.F. of Milling and Resurfacing
|
Project Description:
The project consists of:
Street and Stormwater Improvements.
|
Item
|
Street Description
|
|
A
|
Teke Burton Drive: From Elm Park Drive to Approx. 215’ N. of Orchard Street
|
Approx. 690’x30’ L.F. of Milling and Resurfacing and Stormwater Improvements
|
|
B
|
North Ninth Street: From Hancock Avenue to Portland Street
|
Approx. 310’x24’ L.F. of Milling and Resurfacing.
|
|
C
|
North Ninth Street: From Portland Street to West Main Street
|
Approx. 2050x24 L.F. of Milling and Resurfacing and Curb Ramp Improvements
|
|
D
|
Portland Street: From Ninth Street West to Terminus
|
Approx. 180x35 L.F. of Milling and Resurfacing.
|
|